Erection of scaffolding
In preparation for the work on the façades, we will be erecting scaffolding in the courtyard from 6 March onwards. These preparations will take around two weeks and may cause some noise disturbance.
Façade restoration work
On 13 March, we will commence restoration work on the façades. This will involve the restoration of the masonry and concrete where necessary. Any necessary cutting and drilling will take place outside teaching hours as much as possible. The next step will be to clean the façades.
Window frame painting work
From 20 March, we will restore the window frames where necessary, sand them and paint them. The sanding may be accompanied by noise disturbance. We expect to have completed all work on the façades in the courtyard at the end of May.
More information
Visit the Roeterseiland Campus website for more information about the major maintenance work on building REC J/K. If you have questions about the work, contact omgevingsmanager-rec@uva.nl.