12 July 2023
In preparation for the work on the façade, scaffolding will be erected from 21 August, which will take about a week and may cause some noise disturbance. Construction fences will also be erected in front of the scaffolding.
Repair work on the façade will start on 28 August. The first step will be to clean the façade. After that, the masonry and concrete will be repaired where necessary. This will also involve light chopping and drilling. After the repair work, the frames will be sanded and painted. The sanding may be accompanied by noise disturbance.
The scaffolding is expected to be taken down around mid-October. This may cause some noise disturbance.
Work will start at 7:00 on weekdays.
If you have any questions or comments, please contact the project team at: omgevingsmanager-rec@uva.nl.