23 December 2021
Work is progressing well at LAB42. All the work platforms have been removed and the transformers have been put into place. The glass has also been delivered and is being placed on the first floor and ground floor. Inside, work is being carried out on the ground floor, first and second floors. Among other things, the metal stud walls are being installed here. Doors have already been installed on the sixth floor; things are going really fast there. The installer is also working on cable and pipe ducts. During the Christmas holiday (25 December to 9 January), most of the work will come to a standstill; only the installer will still be in the building, working on a number of things during week 1-2022.
De Vries and Verburg are working hard to make Matrix ONE windproof and waterproof. The atrium roof has now been installed and the façades have been closed. After a week of Christmas holidays, the installation of the final façade finish will begin in the first week of the new year. The dismantling of/in Matrix ONE will also start at this point.
Construction work for the thermal energy sources for Matrix ONE is going well. The drilling of the wells has been completed and the system will be connected during the course of next year.
If you have questions and/or comments about the construction site, the progress of the work or any other matters, please feel free to contact the area manager: Simon de Roo via omgevingsmanager-asp@uva.nl. For now, happy holidays and a happy new year!