  • 3 Feb 2012
    Construction weather report

    The cold front that has hit us so mercilessly this week has also taken its toll on our construction work. A number of activities that were scheduled to take place cannot be carried out due to the severe frost.

  • 27 Jan 2012
    Construction activities on Saturday, 4 February

    On Saturday 4 February, the cooled water pipelines at building D will be connected to the existing refrigeration machine in the courtyard between buildings E and G. Old pipes will be sawn through and fitted with a ...

  • 27 Jan 2012
    Informative meeting on Roeterseiland, 16 January 2012

    On Monday 16 January, an informative meeting for local residents was held in the BAM site office. Over the course of the evening, visitors received extensive information on upcoming construction work at Roeterseiland.

  • 19 Jan 2012
    Construction work during second half of January

    As we reported in Building Update 6, building D (research and laboratory complex for the Faculty of Social and Behavioural Sciences) and I(CREA) have been completed and are currently being furnished. In January, the ...

  • 6 Jan 2012
    Building update #6

    The following construction activities are planned for the coming period at Roeterseiland.